Failed contractor’s £45 million schools to be demolished and rebuilt

But one of the schools says work will take four years, as ministers take legal advice over recouping costs from collapsed construction company

But one of the schools says work will take four years, as ministers take legal advice over recouping costs from collapsed construction company

5 Dec 2023, 10:56

More from this author

Buildings at three almost-new schools will be demolished due to safety concerns

Three schools built by the same construction company at a cost of £45 million will be demolished and rebuilt over safety concerns, as the government seeks legal advice on recovering costs from the failed firm.

But one of the schools has confirmed works will not be completed for four years, while another is still unsure of the location for new buildings.

Sir Frederick Gibberd College, in Essex, Haygrove School, Somerset, and Buckton Fields Primary School, Northampton, were told in August to close their almost-new buildings constructed by Caledonian Modular.

Surveys found buildings at the three schools, closed in August, could not withstand “very high winds or significant snowfall”.

Academies minister Baroness Barran has now confirmed that the Department for Education (DfE) will fund the rebuilding of the schools.

“We have continued to prioritise face-to-face learning during this time and to help schools through this transition phase, we are providing each school with high quality, long term temporary accommodation,” she said in a statement.

Barran thanked parents and pupils for their “patience” over the last five months, and said the new buildings would have “great indoor and outdoor facilities”.

Contracts worth £38 million for the Sir Frederick Gibberd and Haygrove buildings were awarded to Caledonian Modular in 2019 under the DfE’s £3 billion “modern methods of construction” framework.

Under its contract, Caledonian Modular – which went into administration in March 2022 – led design, planning and installation of the schools. 

The firm was also awarded a £6.5 million contract for building works at Buckton Fields.

Following its collapse, two schools it had been contracted to build in Cornwall were demolished before construction was completed after the government identified “defects”.

Surveys carried out at the DfE’s request earlier this year showed buildings at the three schools closed in August could not withstand “very high winds or significant snowfall”.

Temporary buildings still not in place

Closures meant a staggered start to term at the schools, with some pupils being temporarily transferred to other school sites.

Buckton Fields pupils have been educated at Pineham Barns Primary School, which is also run by Preston Hedges Trust.

Pupils will move into “interim buildings” at the Buckton Fields site in February.

The trust’s CEO, Paul Watson, said while it “certainly would not have ever wanted to be in the position” it is currently in, “we are pleased there is now certainty over the existing school building”.

Year 7 pupils at Sir Frederick Gibberd have been temporarily educated at another school ran by The BMAT Education Trust, while its GCSE pupils have been using other schools for specialist science and DT subjects.

BMAT said that a “full suite” of temporary classrooms would open from April, while the permanent building was not expected to be completed until 2027.

Some Haygrove pupils have been educated in temporary classrooms, with others going to a different school site.

But in a letter to parents on Friday, the school said it was still “engaging” with the DfE on details “such as timescales and the location of the new buildings”.

DfE ‘seeking legal advice’ on recouping costs

Documents filed by administrators on Companies House show the DfE was owed £2 million when Caledonian Modular collapsed.

But there were “insufficient funds” to cover unsecured creditors, which included the DfE.

“We are also reviewing our contracts, and seeking legal advice on how we can recover the costs where that contractor was involved,” Barran has now said.

The DfE said it would launch an investigation into the firm in August.

Schools Week also reported in September that the DfE was yet to find construction companies for four new special schools after two firms contracted to do the work – including Caledonian Modular – collapsed.

It emerged yesterday that a new 210-place primary school in Cheshire, due to open in September 2025, would be delayed by at least a year due to the collapse of a construction firm.

Northwich Guardian reported that Cheshire East Council had warned escalating costs because of the delay could lead to the scheme no longer being affordable.

Latest education roles from

Deputy Principal Finance & Facilities – HSDC

Deputy Principal Finance & Facilities – HSDC

FEA

Executive Principal

Executive Principal

Lift Rawlett

Head Teacher

Head Teacher

Green Meadow Primary School

Director of Admissions

Director of Admissions

Greene's College Oxford

Sponsored posts

Sponsored post

Equity and agency for a changing world – how six core skills are transforming inclusive education

There is a familiar thread running through current government policy, curriculum reviews and public debate about education. We are...

SWAdvertorial
Sponsored post

Equitas: ASDAN’s new digital platform putting skills at the heart of learning

As schools and colleges continue to navigate increasingly complex learning needs, the demand for flexible, skills-focused provision has never...

SWAdvertorial
Sponsored post

Bett UK 2026: Learning without limits

Education is humanity’s greatest promise and our most urgent mission.

SWAdvertorial
Sponsored post

Six tips for improving teaching and learning for vocabulary and maths

The more targeted the learning activity to a student’s ability level, the more impactful it will be.

SWAdvertorial

More from this theme

Schools

Speech and language screening pilot reveals ‘shocking’ level of need

Analysis suggests 6 in 10 children given universal screening were found to have speech and language needs

Lydia Chantler-Hicks
Schools

‘Universal RISE’: How will the DfE’s school improvement scheme work?

DfE writes to schools with the lowest attainment rates urging them to engage with optional programme

Lydia Chantler-Hicks
Schools

Schools face £47.5m free school meals expansion shortfall

Leaders say government's plan to increase funding by 5p per meal goes 'nowhere near far enough'

Lydia Chantler-Hicks
Schools

£23m expansion of school edtech and AI pilot

Pilot to launch in September, and to involve primary, secondary and further education settings across England

Lydia Chantler-Hicks

Your thoughts

Leave a Reply

Your email address will not be published. Required fields are marked *

2 Comments

  1. Robert Hardy

    Perhaps time to give schools back to local authorities and reestablish county architects departments. Our children and grandchildren will be paying billions and billions of debt run up by this failed government and it’s incompetant ‘private is always best’ mantra.